Agios Dometios/Metahan Crossing Expansion

Project Title 
Agios Dometios/Metahan Crossing Expansion
Overall Objective 
To improve the flow of vehicles and pedestrians crossing by expanding the Agios Dometios/Metahan Crossing point.
Output
Agios Dometios/Metahan Crossing expanded.
Location
Nicosia, Cyprus
Type of investment
Construction works
Description of investment

The intended works will encompass:

  • Excavation works;
  • Earthworks;
  • Paving;
  • Electrical and mechanical works; and
  • Landscaping.

The boundaries of the project are limited to an area within the UN Buffer Zone.

Intended beneficiary
Direct beneficiaries: Turkish Cypriot community and Greek Cypriot community of Nicosia and its surroundings

Indirect beneficiaries: Turkish Cypriot community and Greek Cypriot community
Scope of works

Traffic at the Agios Dometios/Metahan crossing has been increasing in recent years. It has now reached its maximum capacity. The result is that vehicle queues are very long and crossing time can sometimes exceed 2 hours, especially during the weekends.

Actions taken by UNDP
  1. Preparation of the designs
    Technical Specifications and Bill of Quantities completed in: August 2025
    Final designs completed in: End of October 2025

  2. Procurement of works
    Two RfQs launched at the end of August 2025
    Procurement process completed: 5 November 2025
  3. Implementation
    Contract signature: 7 November 2025
    Expected completion of works: January 2026