Trunk E / Trunk 1 Sewer Reconstruction

Project Title 
Trunk E / Trunk 1 Sewer Reconstruction 
Overall Objective 
To improve wastewater management in Nicosia 
Output
Trunk E and Trunk 1 Sewers reconstructed 
Location
Nicosia, Cyprus 
Type of investment
Construction works 
Description of investment

The intended works encompass:

  • Excavation works;
  • Removal and disposal of asbestos pipes;
  • Laying of pipes;
  • Construction of manholes;
  • Filling and backfilling; and
  • Reinstatement of road surface.

The works are divided in three sections:

  • Trunk E – Urban section in a length of 764 m
  • Trunk 1 – UN Buffer Zone in a length of 710 m
  • Trunk 1 – East Part in a length of 2003 m

In total, 3477 meters of trunk sewer will be reconstructed.

Intended beneficiary

Direct beneficiaries: local community of Nicosia and Municipality of Nicosia

Indirect beneficiaries: all citizens of Nicosia 

Scope of works

The Nicosia sewerage Trunk E was built in 1986 using asbestos pipes. It was a bi-communal project. Since then and after more than 30 years of operation, the original asbestos sections of the network are in a critical state with sections collapsing. In order not to block wastewater flow and risk overflow, the collapsed network is temporarily replaced by an open ditch which entails environmental, health and safety risks.  

In 2000, a 2 km section of the Trunk E was replaced due to the deterioration of the pipes. The Sewerage Board of Nicosia (SBN), responsible for the sections located in the southern parts of the city, completed the rehabilitation of a 1 km section in Nicosia in 2023. In total, 4,200 meters of pipes need to be replaced.

The implementation of the project benefits both communities. 

Actions taken by UNDP

Trunk E – Urban Section

  1. Preparation of the designs
    The preparation of the designs was conducted by the beneficiary. They were finalised in March 2024. UNDP supported the beneficiary in the preparation of the bill of quantities and cost estimate.
  2. Procurement of works
    An Invitation to Bid was launched in April 2024. The procurement process was completed at the beginning of June.
  3. Implementation
    The contract was signed in mid-June 2024. The works started at the end of July. The works were completed in mid-October.

Trunk 1 – UN Buffer Zone

  1. Preparation of the designs
    The preparation of the designs are ongoing. They should be finalised by the beginning of March.
  2. Procurement of works
    ITB expected to be launched in mid-March 2025.
    Procurement process expected to be completed by June 2025.
  3. Implementation
    Expected contract signature: mid-June 2025
    Expected completion of works: November 2025

Trunk 1 – East Part

  1. Preparation of the designs
    The preparation of the designs was conducted by the beneficiary. They were finalised in September 2024. UNDP supported the beneficiary in the preparation of the bill of quantities and cost estimate.
  2. Procurement of works
    An Invitation to Bid was launched in October 2024. The procurement process is ongoing and should be completed at the beginning of March 2025.
  3. Implementation
    Expected contract signature: March 2025
    Expected completion of works: September 2025