Panagia Eleousa Monastery in Rizokarpaso/Dipkarpaz

Preventive Works

Project Overview
Start date of works20 September 2023
End date of works09 October 2023
Type of interventionPreventive Works
Total project cost€18,441.65

 

Main interventions for this site included

  • Vegetation removal and slope formation 4m around the church
  • Removal of woody plants
  • Pointing
  • Crack repair with mortar
  • Repair of existing doors
  • Closing of window openings
  • Lime concrete roof repair
  • New wooden door on the north and west side of church
  • Re-plastering
  • Insulation
  • Wooden Lintels
  • Metal cover for well (75x75 cm)
     

Main interventions at the Monastery building include

  • Vegetation removal and slope formation 4m around the church
  • Joint filling
  • Treatment on top of the walls
  • Stone works- stones from area
  • Rainwater management after vegetation are cleaned and elevations are revealed

Find more photos of this site here.

The project is co-funded by the European Union and implemented by United Nations Development Programme in partnership with the Technical Committee on Cultural Heritage. 