Panagia Eleousa Monastery in Rizokarpaso/Dipkarpaz
Preventive Works
| Project Overview | |
|---|---|
| Start date of works | 20 September 2023 |
| End date of works | 09 October 2023 |
| Type of intervention | Preventive Works |
| Total project cost | €18,441.65 |
Main interventions for this site included
- Vegetation removal and slope formation 4m around the church
- Removal of woody plants
- Pointing
- Crack repair with mortar
- Repair of existing doors
- Closing of window openings
- Lime concrete roof repair
- New wooden door on the north and west side of church
- Re-plastering
- Insulation
- Wooden Lintels
- Metal cover for well (75x75 cm)
Main interventions at the Monastery building include
- Vegetation removal and slope formation 4m around the church
- Joint filling
- Treatment on top of the walls
- Stone works- stones from area
- Rainwater management after vegetation are cleaned and elevations are revealed
Find more photos of this site here.
The project is co-funded by the European Union and implemented by United Nations Development Programme in partnership with the Technical Committee on Cultural Heritage.